Last Updated on August 12, 2021 by Admin 3
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
- Go over the meetings objectives and agenda.
- Brief the team on which tasks have fallen behind schedule and where the project has slack.
- Refer to the risk register to map the risks to issues and mitigation strategies.
- Review the issue log with the project team and identify potential risks.
- Review an Ishikawa diagram with the project team to determine possible causes and effects.