A project manager has updated the project schedule but cannot analyze the schedule performance. Which of the following steps did the project manager miss?

Last Updated on August 13, 2021 by Admin 3

A project manager has updated the project schedule but cannot analyze the schedule performance. Which of the following steps did the project manager miss?

  • Lock the schedule
  • Approve the schedule
  • Baseline the schedule
  • Fast track the schedule