A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?

Last Updated on August 11, 2021 by Admin 3

A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?

  • In the beginning, projects entail a degree of uncertainty that needs to be specified.
  • In the beginning, projects have start and finish dates that require elaboration.
  • In the beginning, projects are part of a program that requires coordination.
  • In the beginning, projects start with detailed inputs that need to be explained.