An active project has a CPI of 0.92. Which of the following can be determined?

Last Updated on August 12, 2021 by Admin 3

An active project has a CPI of 0.92. Which of the following can be determined?

  • The project is currently over budget.
  • The project has a budget surplus.
  • The project is ahead of schedule.
  • The project is behind schedule.