Based on this information, the CPI reflects which of the following about the project?

Last Updated on August 11, 2021 by Admin 3

A project manager is creating the monthly report for top management. The project manager has collected the information below:

AC = 100
PV = 80
EV = 120

Based on this information, the CPI reflects which of the following about the project?

  • It is under budget.
  • It is over budget.
  • It is ahead of schedule.
  • It is behind schedule.
Explanation
“The cost performance index (CPI) is calculated this way:
CPI = EV / AC”

Excerpt From: Kim Heldman. “CompTIA Project+ Study Guide.” iBooks.