Based on this information, which of the following can the key stakeholders determine about the project?

Last Updated on August 11, 2021 by Admin 3

In a project with a ВАС of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

  • The project is under budget and ahead of schedule.
  • The project is over budget and ahead of schedule.
  • The project is under budget and behind schedule.
  • The project is over budget and behind schedule.