The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

Last Updated on August 12, 2021 by Admin 3

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

  • Analyze the critical path and update the WBS with the new feature
  • Add the new feature and reprioritize the product backlog
  • Add the new feature to the next sprint and move the old feature to the following sprint
  • Conduct a retrospective with the team to discuss the change and introduce the feature