The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

Last Updated on August 11, 2021 by Admin 3

A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

  • Assign a different team member to resolve the issue before the next status meeting.
  • Review the issue with the assigned team member to determine a due date.
  • Set a due date to resolve the issue and inform the assigned team member.
  • Report the team member to a functional manager for disciplinary action.