A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
- Revise the project plan.
- Update the issue log.
- Request additional funding.
- Issue a change request.