The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

Last Updated on August 12, 2021 by Admin 3

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

  • Revise the project plan.
  • Update the issue log.
  • Request additional funding.
  • Issue a change request.