The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT?
- Announce the fast track to the project team.
- Modify the schedule
- Initiate a change request.
- Obtain approval.