The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?

Last Updated on August 13, 2021 by Admin 3

A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?

  • Change validation with quality checks
  • Regression planning
  • Identify approval authority
  • Change implementation