The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

Last Updated on August 13, 2021 by Admin 3

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

  • Update the project charter to include the functional manager as a key stakeholder
  • Publish the project schedule to the functional manager
  • Review the communications plan to ensure proper involvement
  • Add the incident to the issue log and seek resolution
  • Ensure the functional manager is on the status report distribution list