Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:
- follow the change process flow and notify the legal department after the change is implemented.
- extend a formal invitation to the legal department representative to join the CCB.
- hold a separate meeting with the legal department representative and ask for approval.
- notify the legal department representative in the event of an upcoming audit.