To have this change approved, the project manager submits a change request that contains which of the following?

Last Updated on August 12, 2021 by Admin 3

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

  • Description, cost difference of the replacement, and WBS
  • Description, justification, and cost
  • Cost difference of the replacement, justification, and communications plan
  • Description, quality impact, and cost