Which of the following are critical for the project manager to provide?

Last Updated on August 11, 2021 by Admin 3

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.

Which of the following are critical for the project manager to provide?

  • Cost, schedule, organizational chart, and risks/issues
  • Risks/issues, cost, RACI chart, and action items
  • Schedule, cost, risks/issues, and milestones
  • Action items, organizational chart, schedule, and NDA