Rather than sending emails to communicate all project information, the project manager:
– Makes telephone calls to key stakeholders for urgent information
– Sends emails for routine information
– Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?
- Prioritizing based on personal preferences
- Tailoring the method based on message content
- Adjusting the method based on confidentiality constraints
- Demonstrating concern for technological factors