Which of the following calculations accurately shows the critical path?

Last Updated on August 11, 2021 by Admin 3

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

PK0-004 Part 08 Q05 004
PK0-004 Part 08 Q05 004

Which of the following calculations accurately shows the critical path?

  • 20 days
  • 39 days
  • 49 days
  • 52 days