Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?

Last Updated on August 13, 2021 by Admin 3

Which of the following charts would indicate the cause and effect of tasks in a project, and for which of the following activities would the chart be used?

  • Histogram, forecasting
  • Ishikawa, quality control
  • Scatter, determining resources
  • Gantt, leveraging resources