Which of the following documents should the project team reference to fast-track the project? (Choose two.)

Last Updated on August 11, 2021 by Admin 3

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.

Which of the following documents should the project team reference to fast-track the project? (Choose two.)

  • Scope management plan
  • Configuration management plan
  • Network diagram
  • Project schedule
  • Project plan