Which of the following is MOST likely to be the first document created by the project manager?

Last Updated on August 11, 2021 by Admin 3

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

  • Project charter
  • Project management plan
  • Project statement of work
  • Project schedule