While developing a project schedule, the project manager is attempting to sequence the following tasks:

Which of the following is the correct sequence for the above tasks?
- F, C, A, E, B, D
- F, E, C, B, A, D
- F, A, B, C, E, D
- D, B, E, F, C, A