Which of the following is the MOST likely reason?

Last Updated on August 11, 2021 by Admin 3

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.

Which of the following is the MOST likely reason?

  • Established communication plan
  • Scope creep
  • Resource constraints
  • Iterative approach