A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
– Project description
– Draft project timeline and schedule
– Rough milestones
– Draft project budget
– Draft resources required
– High-level risk review
Which of the following sections should be included in this document?
- Business information
- Full risk assessment results
- Draft work breakdown structure
- Full resource requirements