Which of the following should the PM do NEXT?

Last Updated on August 12, 2021 by Admin 3

A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.

Which of the following should the PM do NEXT?

  • Crash the schedule.
  • Notify the project team.
  • Initiate a change request.
  • Accept the risk.