Which of the following should the project manager use to answer the question?

Last Updated on August 13, 2021 by Admin 3

A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

  • Project schedule
  • Project management plan
  • Project charter
  • Staffing matrix
0 0 votes