Which of the following ways should the project manager update the risk register?

Last Updated on August 13, 2021 by Admin 3

Risk ID 2 has occurred.

PK0-004 Part 20 Q17 018
PK0-004 Part 20 Q17 018

Which of the following ways should the project manager update the risk register?

  • Add a column for probability and set risk 2 at 100%
  • Change the risk 2 response to backups restored
  • Change the risk 2 status to issue
  • Change the risk 2 owner to PM