Which of the following would be the BEST step for the project manager to take to prevent scope creep?

Last Updated on August 12, 2021 by Admin 3

A Chief Executive Officer (CEO) has approached a project team member to request a project change.

Which of the following would be the BEST step for the project manager to take to prevent scope creep?

  • Deny the CEO’s request.
  • Implement the project change.
  • Submit the request to the CCB.
  • Ask the CEO to follow the communications plan.